|
|
North Carolina Business Court Rules:Â Ordinary Progress Payment Lien Waiver Operates to Waive and Subordinate Lien Priority. Steve Hedges with Sparrow, Wolf & Dennis, PA In North Carolina, mechanic's liens are granted a superior priority:
NCGS §44A-10. Also, in North Carolina, the grounds and consideration required for a general waiver of lien rights are narrowly proscribed:
NCGS §44A-12(f). Accordingly, the typical interpretation in North Carolina is that a contractor has lien rights that date from its "first furnishing;" those lien rights may not be waived generally absent the payment of special consideration, and ordinary progress payment lien waivers operate only to reduce the dollar amount of an otherwise intact lien right for all unpaid sums. In Wachovia Bank v. Superior Construction Corporation, North Carolina Superior Court, Mecklenburg County, 07 CVS 21256, the Court recently addressed the classic priority conflict between a construction lender's deed of trust and a general contractor's lien rights. The general contractor first furnished work on April 22, 2005. The construction lender's deed of trust was recorded May 19, 2005. Accordingly, under NCGS §44A-10, the general contractor's lien rights take priority over the lender's security interest. However, the contractor had made several initial applications for progress payments, for which it had been paid. In connection with those applications, the contractor had submitted an interim lien waiver, stating that the contractor does hereby:
In a separate affidavit, the contractor purported to waive any claim of lien against the property "with regard to the amount of funds actually paid. " Relying upon case law construing situations where a contractor's waiver or subordination of lien rights was expressly bargained for in consideration of obtaining project financing, the Court in Wachovia found that the lender's ordinary funding of progress payments constituted the necessary contractual consideration for a general waiver of rights through May 31, 2005. As a result, the contractor's lien rights were not merely limited to unpaid sums. The contractor was deemed to have waived all lien rights for the period beginning with the date of first furnishing through May 31, 2005. Accordingly, all of the contractor's remaining lien rights, including rights to retainage withheld for the period prior to May 31, 2005, were now inferior to the lender's deed of trust.
The case is on appeal. Steve Hedges 1.See, e.g. , Mace v. Bryant Construction Corp. , 48 N.C.App. 297, 303 (1980).
|