|
|
|
|
Craftworker Training & Certification
Pipeline Corrosion
Control Level 1
- Introduction to the Pipeline Industry (Pipeline Core)
Introduces the pipeline industry, including pipeline products
and flow paths, maps and drawings used in the industry, and
basic pipeline operations.
- Liquid Pipeline General Abnormal Operating Conditions
(pipeline Core)
Introduces the Abnormal Operating Conditions (AOC;) that can
occur on a pipeline or in a pipeline facility.
- Locating Pipeline and Cable (CT 14.1 and 17.5)
Identifies and explains One-Call notification systems and the
methods used to locate pipe and cable.
- Measure Pit Depth and Wall Thickness (CT 8.1, 8.2 and 8.3)
Explains how to use pit gauges to check pit depth, length, and
profile. Describes how to take multiple readings for RSTRENG
data and how to use ultrasonic meters to check pipewall
thickness.
- Inspect Buried and Submerged Pipe When Exposed (CT 5.1,
5.2 and 5.3)
Identifies and explains types of pipe coatings. Describes the
different causes of coating damage.
- Aboveground Pipe Coating and Inspection (CT 7.1, 7.2, 7.3
and 13.2)
Describes aboveground pipe coating types and the causes of
coating damage. Explains how to perform surface preparation
and coating application for aboveground pipe.
- Apply/Repair External Coatings on Buried/Submerged Pipe
(CT 13)
Identifies and explains the desired qualities of buried pipe
coatings. Describes performing field coating repairs.
- Cathodic Protection Measurement (CT 1.1, 1.4, 1.5, 3.1 and
3.2)
Explains the basic theory of cathodic protection and the
methods used to provide protection.
- Test Station Repair (CT 2.1, 2.2, 2.3 and 2.4)
Identifies and explains the types and construction of test
stations. Explains the methods used to attach test station
wires to the pipe.
- Inspect Internal Pipe Surfaces (CT 12)
Describes using ultrasonic gauges to check pipe wall thickness
and pit gauges to check pit dimensions.
- Internal Corrosion Control (CT 10.1, 10.2 and 11)
Explains how corrosion-monitoring probes operate and the
information that is collected.
Pipeline Corrosion Control Level 2
- Install Cathodic Protection Systems (CT 9.2, 9.3 and
9.4)
Describes requirements for planning a CP system, explains
how to select components, and describes installation
techniques for galvanic and impressed current systems.
- Maintain and Repair Rectifiers (CT 4)
Describes the characteristics of CP rectifiers and the
functions of rectifiers and bonds, as well as repair and
adjustment procedures for rectifiers.
- Mitigate Interference (CT 1.3 and 9.1)
Identifies the sources of interference current in a CP
system, including causes and testing.
- Test and Repair Shorted Casings (CT 9.5)
Explains testing casings, including causes of shorted
casings, how to recognize them, and various tests for
shorted casings condition.
- Conduct Close Interval Survey (CT 1.2 and 1.4)
Identifies common close interval survey equipment, including
test lead reels, current interrupters, and data logger and
reference electrodes.
- Performing Coating Inspection (CT 7.3)
Describes required pre-inspection activities, including
surface preparation, degree of cleanliness, profile, and
coating mixing, thickness, adhesion and curing.
- Perform High-Pressure Blasting/Surface Preparation (CT
7.4 and 13.3)
Explains basic abrasive blast system equipment and describes
the characteristics of blast cleaning media.
- Apply Coatings Using Spray Applications (CT 7.6 and
13.5)
Describes types of paint and coating materials, including
pigments, resins, solvents, and additives, including
film-forming and generic coatings and powder coatings.
|
|
|
|